ProjectCodeMeter Reference Traditional Cost Models Report
Report Creation Time 2019-05-17 8:29:16
Software Version Pro v2.0 Unregistered Trial

Settings
Analysis Type Normal
Programmer price per hour $120
Quality Guarantee First Release (v1.0) 3-Sigma
Platform Maturity Popular Stable and Documented
Debugging Tools Complete system Step Emulator / VM / ICE
Project Folder E:\src\Arduino_ino\
Previous Version Folder

COCOMO 81 Basic
Work (Hours) 279.4
Cost $33528

COCOMO 81 Intermediate
Work (Hours) 408.9
Cost $49072
Development Mode Organic
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High

COCOMO II 2000 Nominal
Work (Hours) 335.8
Cost $40298

COCOMO II 2000 Intermediate
Work (Hours) 271.7
Cost $32602
Effective KDSI 0.68
Precedentedness (PREC) High
Development Flexibility (FLEX) High
Architecture or Risk Resolution (RESL) Normal
Team Cohesion (TEAM) High
Process Maturity (PMAT) High
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High
Platform Volatility (PVOL) Low

REVIC 9.2 Nominal
Basic Effort (Hours) 403.3
Requirements Review Phase (Hours) 48.4
Test and Evaluation Phase (Hours) 88.7
Total Effort (Hours) 540.5
Total Cost $64854
Effective KDSI 0.68

REVIC 9.2
Basic Effort (Hours) 385.0
Requirements Review Phase (Hours) 46.2
Test and Evaluation Phase (Hours) 84.7
Total Effort (Hours) 515.9
Total Cost $61904
Development Mode Organic
Effective KDSI 0.68
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High